The Programme Schedule

Completing this work is a huge task and with over 8500 properties throughout Neath Port Talbot to complete, it will naturally take some time.

Below is a table of when we plan to be in each area and which contractor will be completing the work.

ASW (with support from our Copper Foundation)     RT Contractors (with support from our Copper Foundation)  
Area When   Area When

Crynant
Onllwyn
Seven Sisters

Spring 2019 - Winter 2019   Cwmllynfell
GCG
Lower Brynaman
Godre'r Graig
Ystalyfera
Spring 2018 - Summer 2019
Blaengwrach
Glynneath
Resolven
Autumn 2019 - Winter 2020   Alltwen
Pontardawe
Ynysmeudwy
Rhos
Trebanos
Summer 2019 - Summer 2020
Aberdulais
Cilfrew
Caewern
Roman Way
Cadoxton
Longford
Summer 2020 - Spring 2021   Sandfields Little Warren
Sandfields East
Summer 2020 - Winter 2021/2022
Neath North
Tonna
Spring 2021 - Late Summer 2021   Sandfields West Winter 2021/22 - Winter 2022/23

Cimla
Pelenna

Summer 2021 - Summer 2022   Baglan Late Winter 2022/2023 - Summer 2023
Briton Ferry
Neath Town Centre
Melyn
Pencaerau
Summer 2022 - Winter 2024   Cwmavon
Bryn
Oakwood
Summer 2023 - Spring 2024
Skewen
Llandarcy
Jersey Marine
Winter 2023/2024 - Late Summer 2025   Aberavon
Margam
Velindre
Taibach
Goytre
Port Talbot
Spring 2024 - Summer 2024


Note:
The schedule above is just a guide and is subject to change.